UGI will be doing the mill & overlay on Yale Avenue between 21st and 22nd Streets. This work will start on Monday, June 22nd and will likely extend into Tuesday, June 23rd. Shiloh Paving is doing the work on behalf of UGI. Shiloh will have Flagger Force doing the flagging for the project. This work is the result of a gas main relocation project that took place in 2019. The project will involve curb to curb mill and overlay from 22nd street approximately 650 ft to the east and then a single lane overlay from this location to just east of 22nd street. Door knockers are being put out today for all residents affected within the block and the paving equipment will be staged within work area for the most part.