19th and Chestnut Street Project Construction Dates [11/20/20]

The Borough has entered into a contract with Mid State Paving to construct the 19th and Chestnut Street Pedestrian Island.  The contractor expects to perform layout and cutting of the pavement on 11/23 and 11/24.  During the week of 12/7 or 12/14, the Contractor will return to the site to begin excavation, and will then progress to concrete work on the new curbs and ADA ramps.  While a road closure is not anticipated, lane restrictions and flaggers will be used to direct traffic during construction, which may result in delays.  Residents are encouraged to use alternate routes if possible.

 