Camp Hill Public Works has released a tentative construction schedule for the proposed stormwater work on S. 26th Street. Please note that this schedule is very much weather-dependent and is subject to change at any time.

Crews will work to replace a storm pipe and appurtenances in the street. The current pipe is restricted and must be replaced with a larger size. The pipe is primarily in the street and conveys runoff from areas north of Willow Park.

S. 26th Street will be closed during working hours (7 am to 5 pm) and reopened to traffic at the end of each day. Sidewalks will likely be closed in the area while the bulk of the utility work is completed.

Tentative Schedule:

  • Friday, October 25, 2019: Setting up bypass pump system
  • Monday, October 28 through Monday, November 4, 2019:  Bypass pumping , utility relocation work, and pipe and structures installation
  • Remember these dates are subject to change.